On the Ground

Project Progress

Overall Completion
50%

The main excavation of the pond bed is done. The banks still have to be shaped to the planned layout before planting begins.

  1. Complete
    Survey and permission
    January 2026
  2. Under way
    Ground preparation and excavation
    From May 2026
  3. Upcoming
    Ecosystem planting
    Once the banks are shaped
  4. Upcoming
    Water collection and community handover
    To follow

Timeline

January 2026
Phase 1: Survey and Permission
A survey of the map identified Badshahpur Pond as the site. Permission was then sought from the Municipal Corporation of Gurugram.
From May 2026 ยท In progress
Phase 2: Ground Preparation and Excavation
Clearance of accumulated waste and mechanical excavation of the pond bed. Digging was stopped during July and August because of heavy rain, then resumed. The main excavation is done. The banks still have to be shaped to the planned layout, with a gentler upper slope and a planted shelf at the water's edge.
Upcoming
Phase 3: Ecosystem Planting
The plantation drive will begin soon, once the banks are shaped.
Upcoming
Phase 4: First Water Collection & Community Handover
The pond is designed to capture monsoon rains, followed by an assessment of its water retention capacity. Pathways and fencing to be installed, public access opened, and a long-term community stewardship plan activated.